Overview

By default, up.time Uptime Infrastructure Monitor continuously collects data from monitored systems. If you only need to collect data from a system at a particular interval, you can configure monitoring periods and apply them to a service monitor. Monitoring periods are times during which a service monitor will actively monitor a host and send alerts.

...

This article explains how to configure daily,  weekly and  monthly monitoring periods.

...

Getting Started

To configure monitoring periods:

  1. On the up.time Uptime Infrastructure Monitor tool bar, click Services.
  2. In the Services tree panel, click Add Monitoring Period.

...

A daily monitoring period will check a system once per day during a range of times that you specify. To configure a daily monitoring period:

  1. In the Add Monitoring Period window, enter a descriptive name in the Name field.
  2. To create a monitoring period to run every day of the week from 8 AM to 6 PM, enter: Sun-Sat 8am-6pm.
    Image Modified
  3. Click Save.

You can now scroll down to the now Apply the monitoring period to a monitor.

 

...

Configuring a Weekly Monitoring Period

A weekly monitoring period will check a system once or more over a seven-day period during a range of times that you specify. To configure a weekly monitoring period: 

  1. In the Monitoring Periods window, enter a descriptive name in the Monitor Period Name field.
  2. The following example shows how to create a weekly monitoring period that covers Monday, Wednesday and Friday for the entire day. A single day of the week could be similarly specified.
    Image Modified
  3. Click Save.

You can now scroll down to the now Apply the monitoring period to a monitor.

...

Configuring a Monthly Monitoring Period

A monthly monitoring period will check a system once or more over a month, during a range of times that you specify. To configure a monthly monitoring period:

  1. In the Monitoring Periods window, enter a descriptive name in the Monitor Period Name field.
  2. It is possible to specify a numerical day of the month or the day of the week in a specific week of the month. An example of each follows.
    Image Modified

 

  1. Image Modified
  2. Click Save.

You can now scroll down to the now Apply the monitoring period to a monitor.

...

Applying Monitoring Periods to Monitors

...